20190215-EI |
12/06/2019 |
CASR Not Yet Filed |
Petition for approval of depreciation rates for energy storage equipment, by Tampa Electric Company. |
[Docket Filings] |
20190203-EI |
11/13/2019 |
11/21/2019 |
Petition for limited proceeding to reduce base rates and charges to reflect impact of the 2019 temporary state income tax rate reduction, by Tampa Electric Company. |
[Docket Filings] |
20190198-EI |
11/01/2019 |
11/8/2019 |
Petition for approval of modifications to rate schedule SOL-1 shared solar rider experimental pilot program, by Duke Energy Florida, LLC. |
[Docket Filings] |
20190190-EI |
10/07/2019 |
10/23/2019 |
Petition for approval of twelve-month extension of voluntary solar partnership rider and program, by Florida Power & Light Company. |
[Docket Filings] |
20190183-EI |
9/18/2019 |
9/30/2019 |
Petition for approval of a new depreciation class and for energy storage equipment, by Duke Energy Florida, LLC. |
[Docket Filings] |
20190179-EI |
9/09/2019 |
10/10/2019 |
Application for authority to issue and sell securities during calendar years 2020 and 2021, pursuant to Section 366.04, F.S., and Chapter 25-8, F.A.C., by Duke Energy Florida, LLC. |
[Docket Filings] |
20190178-EI |
9/06/2019 |
9/16/2019 |
Application for authority to issue and sell securities for 12 months ending December 31, 2020, by Tampa Electric Company. |
[Docket Filings] |
20190176-EI |
9/05/2019 |
10/24/2019 |
Joint petition for approval of regulatory improvements for decentralized solar net-metering systems in Florida. |
[Docket Filings] |
20190174-EI |
9/03/2019 |
12/9/2019 |
Petition for approval of 2019 depreciation study by Florida Public Utilities Company. |
[Docket Filings] |
20190167-EI |
8/26/2019 |
10/4/2019 |
Petition to compel Florida Power & Light to comply with Section 366.91, F.S. and Rule 25.6-065, F.A.C., by Floyd Gonzales and Robert Irwin. |
[Docket Filings] |
20190164-EI |
8/22/2019 |
8/30/2019 |
Proposed amendment of Rule 25-6.0141, F.A.C., Allowance for Funds Used During Construction; Rule 25-6.033, F.A.C., Tariffs; Rule 25-6.036, F.A.C., Inspection of Plant; and Rule 25-6.037, F.A.C., Extent of System Which Utility Shall Operate and Maintain. |
[Docket Filings] |
20190158-EI |
8/14/2019 |
8/28/2019 |
Application for authority to issue and sell securities during calendar year 2020, pursuant to Section 366.04, F.S., and Chapter 25-8, F.A.C., by Gulf Power Company. |
[Docket Filings] |
20190157-EI |
8/14/2019 |
8/22/2019 |
Application for authority to issue and sell securities during calendar years 2020 and 2021, pursuant to Section 366.04, F.S., and Chapter 25-8, F.A.C., by Florida Power & Light Company and Florida City Gas. |
[Docket Filings] |
20190156-EI |
8/07/2019 |
10/29/2019 |
Petition for a limited proceeding to recover incremental storm restoration costs, capital costs, revenue reduction for permanently lost customers, and regulatory assets related to Hurricane Michael, by Florida Public Utilities Company. |
[Docket Filings] |
20190155-EI |
8/07/2019 |
10/29/2019 |
Petition for establishment of regulatory assets for expenses not recovered during restoration for Hurricane Michael, by Florida Public Utilities Company. |
[Docket Filings] |
20190140-EI |
7/10/2019 |
10/3/2019 |
Petition to approve transaction for accelerated decommissioning services at CR3 facility, transfer of title to spent fuel and associated assets, and assumption of operations of CR3 facility pursuant to the NRC license, and request for waiver from future application of Rule 25-6.04365, F.A.C. for nuclear decommissioning study, by Duke Energy Florida, LLC. |
[Docket Filings] |
20190139-EI |
7/10/2019 |
12/2/2019 |
Complaint against Duke Energy Florida, LLC d/b/a Duke Energy regarding billing errors and inaccurate meter readings, by Elizabeth Randle. |
[Docket Filings] |
20190131-EU |
6/18/2019 |
11/1/2019 |
Proposed adoption of Rule 25-6.030, F.A.C., Storm Protection Plan and Rule 25-6.031, F.A.C., Storm Protection Plan Cost Recovery Clause. |
[Docket Filings] |
20190110-EI |
4/30/2019 |
10/29/2019 |
Petition for limited proceeding for recovery of incremental storm restoration costs related to Hurricane Michael and approval of second implementation stipulation, by Duke Energy Florida, LLC. |
[Docket Filings] |
20190094-EU |
4/17/2019 |
9/16/2019 |
Petition for variance from or waiver of Rule 25-6.049(5) and (6), FAC, by Calypso Tower III, LLC. |
[Docket Filings] |
20190061-EI |
3/13/2019 |
10/7/2019 |
Petition for approval of FPL SolarTogether program and tariff, by Florida Power & Light Company. |
[Docket Filings] |
20190038-EI |
2/06/2019 |
11/13/2019 |
Petition for limited proceeding for recovery of incremental storm restoration costs related to Hurricane Michael, by Gulf Power Company. |
[Docket Filings] |
20190021-EG |
1/15/2019 |
10/23/2019 |
Commission review of numeric conservation goals (Tampa Electric Company). |
[Docket Filings] |
20190020-EG |
1/15/2019 |
10/14/2019 |
Commission review of numeric conservation goals (JEA). |
[Docket Filings] |
20190019-EG |
1/15/2019 |
10/14/2019 |
Commission review of numeric conservation goals (Orlando Utilities Commission). |
[Docket Filings] |
20190018-EG |
1/15/2019 |
10/23/2019 |
Commission review of numeric conservation goals (Duke Energy Florida, LLC). |
[Docket Filings] |
20190017-EG |
1/15/2019 |
10/14/2019 |
Commission review of numeric conservation goals (Florida Public Utilities Company). |
[Docket Filings] |
20190016-EG |
1/15/2019 |
10/14/2019 |
Commission review of numeric conservation goals (Gulf Power Company). |
[Docket Filings] |
20190015-EG |
1/15/2019 |
10/14/2019 |
Commission review of numeric conservation goals (Florida Power & Light Company). |
[Docket Filings] |
20190009-EI |
1/02/2019 |
5/14/2019 |
Nuclear cost recovery clause. |
[Docket Filings] |
20190007-EI |
1/02/2019 |
3/6/2019 |
Environmental cost recovery clause. |
[Docket Filings] |
20190002-EG |
1/02/2019 |
10/29/2019 |
Energy conservation cost recovery clause. |
[Docket Filings] |
20190001-EI |
1/02/2019 |
5/6/2019 |
Fuel and purchased power cost recovery clause with generating performance incentive factor. |
[Docket Filings] |
20180224-EI |
12/05/2018 |
10/1/2019 |
Joint petition for rate reductions or alternative reverse make-whole rate case against Florida Power & Light Company, by Office of Public Counsel, Florida Industrial Power Users Group, and Florida Retail Federation. |
[Docket Filings] |
20180168-EI |
9/07/2018 |
9/12/2018 |
Application for authority to issue and sell securities during calendar years 2019 and 2020, pursuant to Section 366.04, F.S., and Chapter 25-8, F.A.C., by Florida Power & Light Company. |
[Docket Filings] |
20180167-EI |
9/07/2018 |
9/12/2018 |
Application for authority to issue and sell securities for 12 months ending December 31, 2019, by Tampa Electric Company. |
[Docket Filings] |
20180165-EI |
9/05/2018 |
9/13/2018 |
Application for authority to issue and sell securities during 12 months ending December 31, 2019, pursuant to Section 366.04, F.S., and Chapter 25-8, F.A.C., by Duke Energy Florida, LLC. |
[Docket Filings] |
20180162-EI |
8/31/2018 |
1/15/2019 |
Application for authority to issue and sell securities and to receive common equity contributions during 12 months ending December 31, 2019, pursuant to Chapter 25-8, F.A.C., and Section 366.04, F.S., by Gulf Power Company. |
[Docket Filings] |
20180047-EI |
2/21/2018 |
6/6/2019 |
Consideration of the tax impacts associated with Tax Cuts and Jobs Act of 2017 for Duke Energy Florida, LLC. |
[Docket Filings] |
20180046-EI |
2/21/2018 |
12/10/2019 |
Consideration of the tax impacts associated with Tax Cuts and Jobs Act of 2017 for Florida Power & Light Company. |
[Docket Filings] |
20180045-EI |
2/21/2018 |
1/3/2019 |
Consideration of the tax impacts associated with Tax Cuts and Jobs Act of 2017 for Tampa Electric Company. |
[Docket Filings] |
20170057-EI |
2/28/2017 |
4/10/2018 |
Analysis of IOUs' hedging practices. |
[Docket Filings] |
20150171-EI |
7/27/2015 |
12/29/2017 |
Petition for issuance of nuclear asset-recovery financing order, by Duke Energy Florida, Inc. d/b/a Duke Energy. |
[Docket Filings] |
20150148-EI |
5/22/2015 |
11/18/2015 |
Petition for approval to include in base rates the revenue requirement for the CR3 regulatory asset, by Duke Energy Florida, Inc. |
[Docket Filings] |
20140234-EI |
12/08/2014 |
5/4/2018 |
Gulf Power Company's request for confidential treatment of certain information contained in report entitled review of physical security protection of utility substations and control centers. |
[Docket Filings] |
20140233-EI |
12/08/2014 |
5/4/2018 |
Florida Power & Light Company's request for confidential treatment of certain information contained in report entitled review of physical security protection of utility substations and control centers. |
[Docket Filings] |
20080271-EI |
5/13/2008 |
CASR Not Yet Filed |
Status of Joint-Ownership of discussions associated with Florida Power & Light's Turkey Point Units 6 and 7. |
[Docket Filings] |
20060038-EI |
1/13/2006 |
11/1/2019 |
Petition for issuance of a storm recovery financing order, by Florida Power & Light Company. |
[Docket Filings] |