Florida Public Service Commission

FLORIDA PUBLIC SERVICE COMMISSION
SUMMARY OF ORDERS ISSUED
WEEK OF FEBRUARY 26 - 02, 2018

ELECTRIC INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20170272-EI 02/26/2018 PSC-2018-0103-PCO-EI
Order PSC-2018-0103-PCO-EI approving interim storm recovery charge for Duke Energy; approves Duke Energy’s amended implementation stipulation; utility shall file documentation of the actual storm costs once those costs are known; docket to remain open.
Application for limited proceeding for recovery of incremental storm restoration costs related to Hurricanes Irma and Nate, by Duke Energy Florida, LLC.
20180001-EI 02/26/2018 PSC-2018-0105-PCO-EI
Order PSC-2018-0105-PCO-EI approving FPL’s petition for mid-course correction effective with the 3/18 billing cycle; docket to remain open.
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20170272-EI 02/27/2018 PSC-2018-0111-PCO-EI
Order PSC-2018-0111-PCO-EI acknowledging intervention by OPC.
Application for limited proceeding for recovery of incremental storm restoration costs related to Hurricanes Irma and Nate, by Duke Energy Florida, LLC.
20180046-EI 02/27/2018 PSC-2018-0112-PCO-EI
Order PSC-2018-0112-PCO-EI acknowledging intervention by OPC.
Consideration of the tax impacts associated with Tax Cuts and Jobs Act of 2017 for Florida Power & Light Company.
20180039-EI 03/01/2018 PSC-2018-0116-PCO-EI
Order PSC-2018-0116-PCO-EI establishing procedure and provisions of this order to govern this proceeding unless modified by the Commission.
Consideration of the stipulation and settlement agreement between Gulf Power Company, the Office of Public Counsel, Florida Industrial Power Users Group, and Southern Alliance for Clean Energy regarding the Tax Cuts and Jobs Act of 2017.
20170198-EI 02/26/2018 PSC-2018-0106-TRF-EI
Order PSC-2018-0106-TRF-EI approving TECO’s lighting tariff modifications; new proposed tariff shall be effective 2/6/18; if no protest, order to become final and effective on issuance of CO; docket to be closed upon issuance of CO; protest due 3/19/18.
Petition to close to new business all existing lighting rates and approve new LED lighting rates and tariffs, by Tampa Electric Company.
20170248-EI 02/26/2018 PSC-2018-0107-PAA-EI
PAA Order PSC-2018-0107-PAA-EI approving Duke Energy’s fuel cost proxy substitution; if no protest, order to become final and effective on issuance of CO; if order becomes final, docket to be closed; protest due 3/19/18.
Petition for approval of fuel cost proxy substitution to qualifying facility contract between Duke Energy Florida, LLC and CFR/Biogen (n/k/a Orange Cogeneration Limited Partners), Ridge Generating Station Limited Partnership, Mulberry Energy Company, Inc. (n/k/a Polk Power Partners), and Orlando Cogen Limited, L.P.
20170199-EI 02/27/2018 PSC-2018-0110-PAA-EI
PAA Order PSC-2018-0110-PAA-EI approving TECO’s petition for approval of conservation street and outdoor lighting conversion program; order to become final and effective on issuance of CO; docket to be closed if order becomes final; protest due 3/20/18.
Petition for approval of conservation street and outdoor lighting conversion program, by Tampa Electric Company.
20170266-EC 03/01/2018 PSC-2018-0093A-CFO-EC
Amendatory Order PSC-2018-0093A-CFO-EC amending scrivener’s error to reflect that each reference to Document No. 10828-2017 is replaced with Document No. 10831-2017, and each reference to Document No. 10829-2017 is replaced with Document No. 10833-2017; order PSC-2018-0093-CFO-EC is reaffirmed in all other respects.
Petition to determine need for Seminole combined cycle facility, by Seminole Electric Cooperative, Inc.
20170267-EC 03/01/2018 PSC-2018-0093A-CFO-EC
Amendatory Order PSC-2018-0093A-CFO-EC amending scrivener’s error to reflect that each reference to Document No. 10828-2017 is replaced with Document No. 10831-2017, and each reference to Document No. 10829-2017 is replaced with Document No. 10833-2017; order PSC-2018-0093-CFO-EC is reaffirmed in all other respects.
Joint petition for determination of need for Shady Hills combined cycle facility in Pasco County, by Seminole Electric Cooperative, Inc. and Shady Hills Energy Center, LLC.
GAS INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20180003-GU 03/01/2018 PSC-2018-0114-PCO-GU
Order PSC-2018-0114-PCO-GU establishing procedure.
Purchased gas adjustment (PGA) true-up.
20180004-GU 03/01/2018 PSC-2018-0115-PCO-GU
Order PSC-2018-0115-PCO-GU establishing procedure.
Natural gas conservation cost recovery.
TELECOMMUNICATION INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20180033-TA 02/27/2018 PSC-2018-0108-PAA-TA
PAA Order PSC-2018-0108-PAA-TA directing NeuStar to provide TCAL with additional numbering resources for the Port Charlotte rate center (FTMYFKXAX1Z) switch as soon as possible; order to become final and effective on issuance of CO; docket to be closed if order becomes final; protest due 3/20/18.
Petition for expedited review of NXX-X code denial by Number Pooling Administrator for the Port Charlotte rate center, by Teleport Communications America, LLC - FL.
WASTEWATER INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20170141-SU 02/26/2018 PSC-2018-0102-PCO-SU
Order PSC-2018-0102-PCO-SU approving interim rates and surcharge and suspending final rates; authorizing implementation of a one-time charge associated with over-refund in Docket 20150071; K W Resort to maintain a corporate undertaking to guarantee any potential refund of revenues collected under interim conditions; K W Resort to provide a report by the 20th day of each month indicating monthly and total revenue collected subject to refund, pursuant to Rule 25-30.360(6), FAC; utility to file revised tariff sheets and a proposed customer notice to reflect approved rates and provide proof of noticing within 10 days of the date of the notice; approved rates and one-time surcharge are not to be implemented until required security has been filed and staff has approved proposed customer notice; denying interim AFPI charges; docket to remain open.
Application for increase in wastewater rates in Monroe County by K W Resort Utilities Corp.
WATER AND WASTEWATER INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20170255-WS 02/27/2018 PSC-2018-0109-TRF-WS
Order PSC-2018-0109-TRF-WS approving miscellaneous service charges for Deer Creek, effective on or after the stamped approval date on the tariff pursuant to Rule 25-30.475, FAC; if no protest a CO shall be issued; docket to be closed administratively upon staff’s verification that the notice of charge has been given to customers; protest due 3/20/18.
Request for approval of amendment to tariff to charge miscellaneous service charges and to collect customer deposits in Polk County, by Deer Creek RV Golf & Country Club, Inc.
20170270-WS 02/26/2018 PSC-2018-0101-FOF-WS
Final Order PSC-2018-0101-FOF-WS acknowledging transfer of receivership of Four Points from Michael Smallridge to Polk County; cancels Certificate Nos. 634-W and 544-S; dockets to be closed.
Application for acknowledgment of transfer of receivership to Polk County, and cancellation of Certificate Nos. 634-W and 544-S, by Four Points Utility Corporation.
20110254-WS 02/26/2018 PSC-2018-0101-FOF-WS
Final Order PSC-2018-0101-FOF-WS acknowledging transfer of receivership of Four Points from Michael Smallridge to Polk County; cancels Certificate Nos. 634-W and 544-S; dockets to be closed.
Initiation of show cause proceedings against Four Points Utility Corporation in Polk County for violation of Commission rules and regulations as outlined in the Florida Public Service Commission's management audit for Four Points Utility Corporation and Bimini Bay Utilities Corporation issued June 2011.
GENERIC DOCKETS
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20180013-PU 02/26/2018 PSC-2018-0104-PCO-PU
Order PSC-2018-0104-PCO-PU establishing effective dates of 2/6/18 for adjustments associated with the Tax Cuts and Jobs Act of 2017 for utilities that do not have settlement agreements; utilities that have settlement agreements addressing this issue, the terms of each settlement agreement addressing the effective date for adjustments associated with the Tax Cuts and Jobs Act of 2017 shall control; docket to remain open.
Petition to establish a generic docket to investigate and adjust rates for 2018 tax savings, by Office of Public Counsel.
20180008-OT 02/28/2018 PSC-2018-0113-FOF-OT
Final Order PSC-2018-0113-FOF-OT authorizing appearance as qualified representative to Dulaney L. O’Roark III for MCI Communications Services, Inc. d/b/a Verizon Business Services, and MCImetro Access Transmission Services Corp. d/b/a Verizon Access Transmission Services, Verizon Long Distance LLC, Verizon Select Services Inc. and XO Communications Services, LLC.
Applications for qualified representative status.