DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20170001-EI 01/02/2018 PSC-2018-0001-PCO-EI
Order PSC-2018-0001-PCO-EI establishing 2018 docket number. [CLK note: Docket 20170001 will be closed on issuance of this order.]
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20180001-EI 01/02/2018 PSC-2018-0001-PCO-EI
Order PSC-2018-0001-PCO-EI establishing 2018 docket number. [CLK note: Docket 20170001 will be closed on issuance of this order.]
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20170231-EI 01/05/2018 PSC-2018-0015-CFO-EI
Order PSC-2018-0015-CFO-EI granting FPL’s request for confidential classification (of DN 09344-2017) for a period of up to 18 months from the date of issuance of this order.
Petition for approval to transfer Martin- Riviera Lateral Pipeline to Florida Southeast Connection and implement associated rate adjustments, by Florida Power & Light Company.
20170231-EI 01/05/2018 PSC-2018-0016-CFO-EI
Order PSC-2018-0016-CFO-EI granting FPL’s request for confidential classification (of DN 10368-2017) for a period of up to 18 months from the date of issuance of this order.
Petition for approval to transfer Martin- Riviera Lateral Pipeline to Florida Southeast Connection and implement associated rate adjustments, by Florida Power & Light Company.
20170002-EG 01/02/2018 PSC-2018-0002-PCO-EG
Order PSC-2018-0002-PCO-EG establishing 2018 docket number. [CLK note: Docket 20170002 will be closed on issuance of this order.]
Energy conservation cost recovery clause.
20180002-EG 01/02/2018 PSC-2018-0002-PCO-EG
Order PSC-2018-0002-PCO-EG establishing 2018 docket number. [CLK note: Docket 20170002 will be closed on issuance of this order.]
Energy conservation cost recovery clause.
20170007-EI 01/02/2018 PSC-2018-0007-PCO-EI
Order PSC-2018-0007-PCO-EI establishing 2018 docket number. [CLK note: Docket 20170007 will be closed on issuance of this order.]
Environmental cost recovery clause.
20180007-EI 01/02/2018 PSC-2018-0007-PCO-EI
Order PSC-2018-0007-PCO-EI establishing 2018 docket number. [CLK note: Docket 20170007 will be closed on issuance of this order.]
Environmental cost recovery clause.
20180007-EI 01/05/2018 PSC-2018-0014-FOF-EI
Final Order PSC-2018-0014-FOF-EI approving projected expenditures and true-up amounts for environmental cost recovery; each utility that was a party to this docket shall abide by the stipulations and findings which are applicable to it; land conveyance from FPL to SFWMD is neither approved nor denied; FPL’s approved costs associated with the CA, CAA, and CO are part of the existing monitoring plan project and proposed allocations are approved; utilities named in order are authorized to collect the environmental cost recovery amounts and use the factors approved for billing cycles 1/18-12/18; revised tariffs reflecting the environmental cost recovery amounts and factors determined to be appropriate in this proceeding are approved; docket to remain open.
Environmental cost recovery clause.
20170009-EI 01/02/2018 PSC-2018-0009-PCO-EI
Order PSC-2018-0009-PCO-EI establishing 2018 docket number. [CLK note: Docket 20170009 will be closed on issuance of this order.]
Nuclear cost recovery clause.
20180009-EI 01/02/2018 PSC-2018-0009-PCO-EI
Order PSC-2018-0009-PCO-EI establishing 2018 docket number. [CLK note: Docket 20170009 will be closed on issuance of this order.]
Nuclear cost recovery clause.
20170266-EC 01/05/2018 PSC-2018-0018-PCO-EC
Order PSC-2018-0018-PCO-EC establishing procedure and consolidating Dockets 20170266-EC and 20170267-EC for hearing.
Petition to determine need for Seminole combined cycle facility, by Seminole Electric Cooperative, Inc.
20170267-EC 01/05/2018 PSC-2018-0018-PCO-EC
Order PSC-2018-0018-PCO-EC establishing procedure and consolidating Dockets 20170266-EC and 20170267-EC for hearing.
Joint petition for determination of need for Shady Hills combined cycle facility in Pasco County, by Seminole Electric Cooperative, Inc. and Shady Hills Energy Center, LLC.
GAS INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20170003-GU 01/02/2018 PSC-2018-0003-PCO-GU
Order PSC-2018-0003-PCO-GU establishing 2018 docket number. [CLK note: Docket 20170003 will be closed on issuance of this order.]
Purchased gas adjustment (PGA) true-up.
20180003-GU 01/02/2018 PSC-2018-0003-PCO-GU
Order PSC-2018-0003-PCO-GU establishing 2018 docket number. [CLK note: Docket 20170003 will be closed on issuance of this order.]
Purchased gas adjustment (PGA) true-up.
20170004-GU 01/02/2018 PSC-2018-0004-PCO-GU
Order PSC-2018-0004-PCO-GU establishing 2018 docket number. [CLK note: Docket 20170004 will be closed on issuance of this order.]
Natural gas conservation cost recovery.
20180004-GU 01/02/2018 PSC-2018-0004-PCO-GU
Order PSC-2018-0004-PCO-GU establishing 2018 docket number. [CLK note: Docket 20170004 will be closed on issuance of this order.]
Natural gas conservation cost recovery.
20170179-GU 01/04/2018 PSC-2018-0011-PCO-GU
Order PSC-2018-0011-PCO-GU approving interim rates and suspending proposed final rates for FCG; any interim revenue increase authorized shall be applied evenly across the board to all rate classes based on their base rate revenues, and shall be collected on a cents-per-therm basis; interim rates shall be made effective on or after 30 days from the date of Commission’s vote, 12/12/17; FCG shall notice customers of the revised rates; utility shall file revised tariff sheets and a proposed customer notice to reflect Commission’s approved rates; docket to remain open pending Commission’s final action on requested final rates.
Petition for rate increase by Florida City Gas.
TELECOMMUNICATION INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20170250-TL 01/05/2018 PSC-2018-0017-CO-TL
Consummating order PSC-2018-0017-CO-TL makes order PSC-2017-0463-PAA-TL effective and final; docket to be closed.
Petition for expedited review of NXX-X code denial by North American Numbering Plan Administration for Bonita Springs exchange, by Embarq Florida, Inc. d/b/a CenturyLink.
WATER AND WASTEWATER INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20170005-WS 01/02/2018 PSC-2018-0005-PCO-WS
Order PSC-2018-0005-PCO-WS establishing 2018 docket number. [CLK note: Docket 20170005 will be closed on issuance of this order.]
Annual reestablishment of price increase or decrease index of major categories of operating costs incurred by water and wastewater utilities pursuant to Section 367.081(4)(a), F.S.
20180005-WS 01/02/2018 PSC-2018-0005-PCO-WS
Order PSC-2018-0005-PCO-WS establishing 2018 docket number. [CLK note: Docket 20170005 will be closed on issuance of this order.]
Annual reestablishment of price increase or decrease index of major categories of operating costs incurred by water and wastewater utilities pursuant to Section 367.081(4)(a), F.S.
20170006-WS 01/02/2018 PSC-2018-0006-PCO-WS
Order PSC-2018-0006-PCO-WS establishing 2018 docket number. [CLK note: Docket 20170006 will be closed on issuance of this order.]
Water and wastewater industry annual reestablishment of authorized range of return on common equity for water and wastewater utilities pursuant to Section 367.081(4)(f), F.S.
20180006-WS 01/02/2018 PSC-2018-0006-PCO-WS
Order PSC-2018-0006-PCO-WS establishing 2018 docket number. [CLK note: Docket 20170006 will be closed on issuance of this order.]
Water and wastewater industry annual reestablishment of authorized range of return on common equity for water and wastewater utilities pursuant to Section 367.081(4)(f), F.S.
GENERIC DOCKETS
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20170008-OT 01/02/2018 PSC-2018-0008-PCO-OT
Order PSC-2018-0008-PCO-OT establishing 2018 docket number. [CLK note: Docket 20170008 will be closed on issuance of this order.]
Applications for qualified representative status.
20180008-OT 01/02/2018 PSC-2018-0008-PCO-OT
Order PSC-2018-0008-PCO-OT establishing 2018 docket number. [CLK note: Docket 20170008 will be closed on issuance of this order.]
Applications for qualified representative status.
20180008-OT 01/04/2018 PSC-2018-0010-FOF-OT
Final Order PSC-2018-0010-FOF-OT authorizing appearance as qualified representative to R. Wade Litchfield for FPL.
Applications for qualified representative status.
20180008-OT 01/05/2018 PSC-2018-0012-FOF-OT
Final Order PSC-2018-0012-FOF-OT authorizing appearance as qualified representative to Laura A. Wynn for White Springs.
Applications for qualified representative status.
20180008-OT 01/05/2018 PSC-2018-0013-FOF-OT
Final Order PSC-2018-0013-FOF-OT authorizing appearance as qualified representative to James W. Brew for White Springs.
Applications for qualified representative status.