Florida Public Service Commission

FLORIDA PUBLIC SERVICE COMMISSION
SUMMARY OF ORDERS ISSUED
WEEK OF JULY 23 - 27, 2018

ELECTRIC INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20160251-EI 07/24/2018 PSC-2018-0359-FOF-EI
Final Order PSC-2018-0359-FOF-EI granting joint motion for approval of settlement agreement between OPC and FPL dated 5/15/18 and approving the stipulation and settlement agreement; approving a one-time 2018 interim storm restoration recovery refund starting on 8/1/18; staff shall have administrative authority to approve 2018 interim storm restoration recovery refund tariff sheets consistent with ruling; if no timely appeal, docket to be closed.
Petition for limited proceeding for recovery of incremental storm restoration costs related to Hurricane Matthew by Florida Power & Light Company.
20180001-EI 07/24/2018 PSC-2018-0360-CFO-EI
Order PSC-2018-0360-CFO-EI granting TECO's second request for extension of confidential classification of (DN 02278-2014, x-ref. 01992-2014) for a period of 18 months from the date of this order.
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20180001-EI 07/24/2018 PSC-2018-0361-CFO-EI
Order PSC-2018-0361-CFO-EI granting TECO's second request for extension of confidential classification of (DN 02467-2014, x-ref. 02128-2014 ) for a period of 18 months from the date of this order.
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20180001-EI 07/24/2018 PSC-2018-0362-CFO-EI
Order PSC-2018-0362-CFO-EI granting GPC's request for confidential classification (of DN 03749-2018, x-ref. 03343-2018) for a period of 18 months from the date of this order.
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20180001-EI 07/24/2018 PSC-2018-0363-CFO-EI
Order PSC-2018-0363-CFO-EI granting GPC's request for confidential classification (of DN 03751-2018, x-ref. 03341-2018) for a period of 18 months from the date of this order.
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20170235-EI 07/25/2018 PSC-2018-0370-PCO-EU
Order PSC-2018-0370-PCO-EU establishing procedure; provisions of this order are to govern this proceeding unless modified by the Commission.
Petition by Florida Power & Light Company (FPL) for authority to charge FPL rates to former City of Vero Beach customers and for approval of FPL's accounting treatment for City of Vero Beach transaction.
20180086-EI 07/23/2018 PSC-2018-0356-CO-EI
Consummating Order PSC-2018-0356-CO-EI makes Order PSC-2018-0319-TRF-EI effective and final; docket to be closed.
Petition for approval of revised underground residential distribution tariffs, by Tampa Electric Company.
20170236-EU 07/25/2018 PSC-2018-0370-PCO-EU
Order PSC-2018-0370-PCO-EU establishing procedure; provisions of this order are to govern this proceeding unless modified by the Commission.
Joint petition to terminate territorial agreement, by Florida Power & Light and the City of Vero Beach.
20180084-EI 07/23/2018 PSC-2018-0355-PCO-EI
Order PSC-2018-0355-PCO-EI acknowledging intervention by OPC.
Petition for limited proceeding for approval to include in base rates the revenue requirement for the Citrus combined cycle project, by Duke Energy Florida, LLC.
20180084-EI 07/25/2018 PSC-2018-0367-TRF-EI
Order PSC-2018-0367-TRF-EI approving Duke Energy’s petition for limited proceeding to include in base rates the revenue requirement for citrus combined cycle project; staff is granted administrative authority to approve tariffs and associated charges that implement Commission’s vote regarding citrus combined cycle project; Phase 1's tariffs and associated charges shall go in effect with the first billing cycle in 10/18; Phase 2's tariffs and associated charges shall go in effect with the first billing cycle in 12/18; if the commercial in-service date of Phase 1 is delayed, the tariff shall become effective with the first billing cycle after Phase 1 is completed and placed in commercial service; if Phase 2 is delayed, the tariff shall become effective with the first billing cycle after Phase 2 is completed and placed in commercial service; if protested, Duke Energy shall implement the rates subject to refund pending results of any subsequent hearing; if no protest, docket to be closed on issuance of a CO; protest due 8/15/18.
Petition for limited proceeding for approval to include in base rates the revenue requirement for the Citrus combined cycle project, by Duke Energy Florida, LLC.
20180125-EU 07/23/2018 PSC-2018-0357-PCO-EU
Order PSC-2018-0357-PCO-EU setting procedure to consider GPC’s motion for summary final order; parties may conduct limited discovery as set forth in Section V; may file affidavits as set forth in Section IV; and file briefs on the issues raised in Section III; GPC’s motions for protective orders are denied; GCEC’s motion for status conference is moot; the provisions of this order are to govern this proceeding unless modified by the Commission.
Complaint against Gulf Power Company for expedited enforcement of territorial order, by Gulf Coast Electric Cooperative, Inc.
GAS INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20170265-GU 07/25/2018 PSC-2018-0368-PAA-GU
PAA Order PSC-2018-0368-PAA-GU approving new depreciation rates for SJNG; 1/1/18 is the implementation date for the depreciation rates; company shall file detailed calculations of the revised ITC amortization at the same time it files its earnings surveillance report covering the period ending 12/31/18, per Rule 27-7.1352, FAC; if no protest, order to become final and effective on issuance of a CO; docket to be closed; protest due 8/15/18.
Application for approval of new depreciation rates effective January 1, 2018, by St. Joe Natural Gas Company, Inc.
TELECOMMUNICATION INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20180118-TL 07/25/2018 PSC-2018-0364-PCO-TL
Order PSC-2018-0364-PCO-TL lifting suspension of 689 overlay of 407/321 numbering plan area; NANPA shall notify Commission of proposed implementation date for 689 overlay; docket to remain open.
Implementation of the 689 area code overlay in the existing 407/321 area code.
20180099-TP 07/25/2018 PSC-2018-0369-PCO-TP
Order PSC-2018-0369-PCO-TP approving appointment of Elizabeth Bradin to the Telecommunications Access System Act [TASA] Advisory Committee effective immediately.
Commission approval of Florida Telecommunications Relay, Inc.'s 2018-2019 proposed budget.
WATER INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20180059-WU 07/25/2018 PSC-2018-0366-CO-WU
Consummating Order PSC-2018-0366-CO-WU makes Order PSC-2018-0331-TRF-WU effective and final; docket to remain open.
Application for approval of tariff for the gross-up of CIAC in Escambia County, by Peoples Water Service Company of Florida, Inc.
WATER AND WASTEWATER INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20180042-WS 07/25/2018 PSC-2018-0365-CO-WS
Consummating Order PSC-2018-0365-CO-WS makes Order PSC-2018-0330-TRF-WS effective and final; docket to remain open.
Application for approval of tariff for the gross-up of CIAC in Martin County, by Indiantown Company, Inc.
20170178-WS 07/24/2018 PSC-2018-0358-CO-WS
Consummating Order PSC-2018-0358-CO-WS makes Order PSC-2018-0328-PAA-WS effective and final; docket to remain open.
Application for original certificates of authorization for existing utility currently charging for water and wastewater service in Polk County, by Coastal Income Properties - The Harbor, LLC d/b/a The Harbor.