For an official paper copy, contact the Florida Public Service Commission at contact@psc.state.fl.us or call (850) 413-6770. There may be a charge for the copy.
State of Florida
Public Service
Commission
Capital Circle Office Center 2540 Shumard
Oak Boulevard
Tallahassee, Florida 32399-0850
-M-E-M-O-R-A-N-D-U-M-
DATE: |
||
TO: |
Director, Division of the Commission Clerk & Administrative Services (Bayó) |
|
FROM: |
Division of Economic Regulation (Baxter, Draper, Lee) Office of the General Counsel (Brown) |
|
RE: |
||
AGENDA: |
05/16/06 – Tariff Filing – Interested Persons May Participate |
|
COMMISSIONERS ASSIGNED: |
||
PREHEARING OFFICER: |
||
03/07/06 (60-Day Suspension Date) 09/01/06 (8-Month Effective Date) |
||
SPECIAL INSTRUCTIONS: |
||
FILE NAME AND LOCATION: |
||
On January 6, 2006, Progress Energy Florida (PEF) filed a petition for Commission approval of revisions to its Underground Residential Distribution (URD) tariffs and their associated charges. The Commission suspended the tariff in Order No. PSC-06-0206-PCO-EI, issued March 14, 2006. On March 15, 2006, PEF filed responses to the staff’s data requests that contained clarifications and additional documentation.
Rule 25-6.078, Florida Administrative Code, requires investor-owned electric utilities to file updated underground residential distribution charges for Commission approval at least every three years, or sooner if a utility’s underground cost differential for the standard low-density subdivision varies from the last approved charge by 10 percent or more. PEF’s current URD charges were approved in Order No. PSC-04-0519-TRF-EI, issued on May 24, 2004, in Docket No. 031122-EI, In re: Petition for approval of revised underground residential distribution tariffs by Progress Energy Florida, Inc. To comply with the 3-year filing requirement of the rule, PEF filed this petition.
The Commission has jurisdiction over this matter pursuant to Sections 366.03, 366.04, 366.05, and 366.06, Florida Statutes.
Issue 1: Should the Commission approve PEF’s revised Underground Residential Distribution tariffs and their associated charges?
Recommendation: Yes. (Baxter, Draper, Lee)
Staff Analysis: The URD charges represent the additional costs PEF incurs to provide underground distribution service in place of overhead service, and are calculated as differentials between the cost of underground and overhead service. Costs for underground service have historically been higher than for standard overhead construction. The URD differential is paid by the customer as a contribution-in-aid-of-construction. The URD tariffs provide standard charges for certain types of underground service, and apply to new residential developments such as subdivisions and townhouses.
PEF developed URD charges based on three model subdivisions: (1) a 210-lot low-density subdivision with a density of one or more, but less than six, dwelling units per acre; (2) a 176-lot high-density subdivision with a density of six or more dwelling units per acre; and (3) a high-density subdivision where service is provided using grouped meter pedestals. Examples of the grouped meter pedestals subdivision type include mobile home and R.V. parks. All four major investor-owned electric utilities use the same standardized model subdivisions to develop their URD charges.
As stated in Rule 25-6.115, F.A.C., the URD differential is developed by estimating the cost per lot of both underground service and overhead service, and is based on the utility’s standard engineering and design practices. The difference between these numbers is the per-lot charge that customers must pay when they request underground service in lieu of standard overhead service. The costs of both underground and overhead service include the material and labor costs to provide primary, secondary, and service distribution lines, and transformers. The cost to provide underground service also includes the cost of trenching and backfilling. The utilities are required to use current cost data.
The following table shows PEF’s current and proposed URD differentials:
Type of Subdivision |
Current URD differential per lot |
Proposed URD differential per lot |
Percent Change |
210-lot low density |
$350 |
$428 |
+22% |
176-lot high density |
$224 |
$256 |
+14% |
Grouped meter pedestals |
$130 |
$165 |
+27% |
PEF cited three reasons for the increase in the differential: the use of more conduit, higher labor rates, and removal of the tree trimming costs from the differential calculation.
Conduit. The primary factor driving the increase in the URD differentials is the increased use of conduit by PEF in the installation of its underground primary cables. The term “conduit” as used by PEF refers to three types of pvc tubing (2 inches, 2.5 inches, and 4 inches) that are used to shield cables buried in the ground. During the last URD filing, PEF notified the Commission that the company had adopted a new set of engineering standards as to when and where conduit should be used, which was referenced in Order No. PSC-04-0519-TRF-EI, issued May 24, 2004, in Docket No. 031122-EI, In re: Petition for Approval of Revised Underground Residential Distribution Tariffs by Progress Energy Florida, Inc. PEF now uses conduit in soil with sharp objects such as rocks or shells (if clean fill dirt is unavailable), under pavement, landfills, septic fields, wetlands, creek crossings, retaining walls used for elevation changes, railroad crossings, areas where other underground buried utilities cross PEF’s lines (as required by code and regulation), between side and back lot lines in medium and high density subdivisions, and in congested areas where repair access to the underground cable is not readily available.
The increased use of conduit has a larger impact on low-density subdivisions than high-density subdivisions. Low-density subdivisions tend to have higher conduit and material costs since their lighter housing density requires more material on a relative per-house basis. For example, a 100 foot trench with conduit dug to serve a low-density subdivision, where there are typically 1-6 homes per acre, might serve only one home. Whereas in a high-density subdivision, where there are six or more homes per acre, that trench might serve 1-3 homes.
Grouped-meter pedestal subdivisions have also been effected by increased transformer, conduit, and trenching costs. Although this group shows the largest percentage increase, modest increases in material and labor costs can translate into disproportionately large percentage increases to the grouped-meter subdivision differential because of the lower initial URD.
Labor. PEF hired outside contractors to do its underground service work while overhead service work was done primarily by company employees. PEF stated that underground contract labor rates rose by 3.39% in 2005. The increase in labor costs was driven by escalator clauses in long term labor contracts PEF had signed, a tightening in the labor market, and due to the increased use of conduit. Placing conduit around cable increases the amount of labor needed since the conduit must be laid in the trench and a machine set up to pull the bulk feeder and primary cables through the conduit. PEF asserted that even with the increases in labor costs, it was still more cost efficient to use outside contractors, since the amount of additional company employees required to perform the underground work throughout PEF’s service territory would cause significant increases in personnel and benefits costs.
Tree Trimming. A final factor driving the increase in URD differentials for all three subdivisions was the Commission’s decision in Order No. PSC-04-0187-TRF-EI, issued February 23, 2004, in Docket No. 031107-EI, In re: Petition for Approval of Revisions to Sections 3.02 and 3.05 of Part III, New Service Extensions, Tariff Rules and Regulations by Progress Energy Florida, Inc. to eliminate the costs for the initial clearing of trees from the calculation of contribution-in-aid-of construction for the extension of overhead distribution facilities. PEF proposed and the Commission approved these tariff changes since they made the rules governing provision of overhead distribution consistent with the rules for provision of underground distribution (where customers are responsible for clearing their property) and afforded customers an option to have the work done by a third party, at a potentially lower cost than the utility.
In addition to the proposed changes for the three standard subdivisions, PEF proposed increases to the credits they offer to customers who choose to do their own trenching and backfilling. The proposed increase in the credits reflects PEF’s avoided increased material and labor costs to perform those services. PEF has proposed to increase the trenching and backfilling credit from $1.36 per foot of service lateral, secondary, and primary cable to $1.40 per foot.
PEF also proposed changes to various miscellaneous and contribution in aid of construction charges for provision of underground service. The increases are driven by rising labor and material costs. If feeder mains have to be provided for underground service to a subdivision (either at the request of the customer or due to local regulation), PEF proposed to increase the three-phase primary main or feeder charge per trench-foot within a subdivision from $4.37 to $5.34 per foot for a #1/0 AWG underground vs. #1/0 AWG overhead, from $14.23 to $15.84 per foot for a 500 MCM (measurement of cable size) underground vs. 336 MCM overhead, and from $18.08 to $18.62 per foot for a 1000 MCM underground vs. 795 MCM overhead. For new underground service laterals from overhead distribution systems, PEF proposed the contribution provided by the applicant would increase from $355.00 to $364.50 for service laterals up to 80 feet and from $.60 to $1.20 per foot for service laterals from 81-300 feet. For underground service laterals replacing existing residential overhead services, PEF proposed the contribution provided by the applicant would increase from $257.20 to $258.30 for service laterals up to 80 feet and decrease from $.96 to $.82 per foot for service laterals from 81-300 feet.
PEF stated the benefits of increased use of conduit are: a reduction in the number of outages and replacements required, a reduction in the service time for those cables that do have to be repaired and replaced, and protection of the cable from certain types of excavations.
Staff has reviewed the proposed charges and accompanying work papers. Based on a review of the information provided, staff believes the proposed charges are reasonable, and should be approved.
Issue 2: Should this docket be closed?
Recommendation: Yes. If Issue 1 is approved, this tariff should become effective on May 16, 2006. If a protest is filed within 21 days of the issuance of the order, this tariff should remain in effect, with any revenues held subject to refund, pending resolution of the protest. If no timely protest is filed, this docket should be closed upon the issuance of a consummating order. (Brown)
Staff Analysis: If Issue 1 is approved, this tariff should become effective on May 16, 2006. If a protest is filed within 21 days of the issuance of the order, this tariff should remain in effect, with any revenues held subject to refund, pending resolution of the protest. If no timely protest is filed, this docket should be closed upon the issuance of a consummating order.