WARNING:

Changes in appearance and in display of formulas, tables, and text may have occurred during translation of this document into an electronic medium. This HTML document may not be an accurate version of the official document and should not be relied on.

For an official paper copy, contact the Florida Public Service Commission at contact@psc.state.fl.us or call (850) 413-6770. There may be a charge for the copy.

 

 

DATE:

October 4, 2012

TO:

Office of Commission Clerk (Cole)

FROM:

Division of Engineering (Brady, Rieger)

Office of the General Counsel (Lawson)

RE:

Docket No. 120158-SU – Application for original certificate for an existing wastewater system, requesting initial rates and charges in Lake County by Harbor Waterworks, Inc.

AGENDA:

10/16/12Regular Agenda – Proposed Agency Action for Issues 2, 3, and 4 – Interested Persons May Participate

COMMISSIONERS ASSIGNED:

All Commissioners

PREHEARING OFFICER:

Graham

CRITICAL DATES:

November 5, 2012 (Statutory deadline for original certificate pursuant to Section 367.031, Florida Statutes)

SPECIAL INSTRUCTIONS:

Place on Agenda after Docket No. 120148-WU

FILE NAME AND LOCATION:

S:\PSC\ENG\WP\120158.RCM.DOC

 

Case Background

On May 17, 2012, Harbor Waterworks, Inc. (HWW or Utility), filed an application for an original wastewater certificate in Lake County.  The Utility is located in the St. Johns River Water Management District (SJRWMD) within a water resource caution area.  At the time of the application, the wastewater system was serving 55 residential and 3 general service customers for a total of 76 equivalent residential connections (ERCs).  Water service is also being provided by HWW pending approval of the transfer of Certificate No. 522-W in Docket No. 120148-WU.[1]  While the water system serves approximately 592 residential and 27 general service customers, most of those customers have septic tanks.  A small portion of water customers who do not have septic tanks are served by the wastewater system.

According to the application, the wastewater system has been operational and continuously providing service since 1989.  However, since there was no charge for service, the system was not jurisdictional pursuant to the definition of a utility in Section 367.021(12), Florida Statutes (F.S.).  The wastewater system was acquired by HWW via an Asset Purchase Agreement (Purchase Agreement) executed on or about February 28, 2012.  HWW filed a completed application with respect to a certificate of authorization and initial rates and charges on May 17, 2012. 

Pursuant to Section 367.031, F.S., the Commission shall grant or deny an application for a certificate of authorization within 90 days after the official filing date of the completed application.  HWW’s application was timely protested on June 4, 2012, which stayed the 90-day clock.  Staff conducted a noticed, informal meeting between Commission staff and interested persons on July 31, 2012.  Subsequent to this meeting, the protest to the application for certificate was withdrawn on August 3, 2012.  Therefore, the application for certificate must be ruled upon by November 5, 2012, pursuant to Section 367.031, F.S.

On July 10, 2012, prior to the withdrawal of the protest to the application, HWW filed a letter requesting approval of emergency financial relief by authorization to charge customers a monthly flat rate of $35.00, subject to refund, until final rates were established.  By letter dated July 23, 2012, legal staff explained that neither the Florida Statutes nor the rules of this Commission contemplated approval of rates of any utility prior to certification.  As such, the request for emergency rates was premature.  Staff conducted a customer meeting on September 5, 2012, in the Harbor Hills community to gather customer comments with regard to HWW’s proposed rates and charges.

This recommendation addresses the original wastewater certificate and initial rates and charges.  The Commission has jurisdiction pursuant to Sections 367.031, 367.045, 367.081, and 367.091, F.S.

 


Discussion of Issues

Issue 1

 Should the application of HWW for a wastewater certificate be approved?

Recommendation

 Yes.  The application is in the public interest and HWW should be granted Certificate No. 565-S to serve the territory described in Attachment A, effective the date of the Commission’s vote.  The resultant order should serve as HWW’s wastewater certificate and it should be retained by the Utility.  (Brady, Rieger, Lawson)

Staff Analysis

 On May 17, 2012, HWW filed an application for a wastewater certificate and initial rates and charges for a portion of the Harbor Hills development in Lake County.  The application is in compliance with the governing statute, Section 367.045, F.S., and other pertinent statutes and administrative rules concerning an application for original certificate.

Noticing

The application contains evidence of compliance with the noticing provisions set forth in Rule 25-30.030, Florida Administrative Code (F.A.C.).  Pursuant to Section 367.031, F.S., the Commission shall grant or deny an application for a certificate of authorization within 90 days after the official filing date of the completed application.  As noted, a timely customer protest was filed on June 4, 2012, which stayed the 90-day clock.  A noticed, informal meeting between Commission staff and interested persons was conducted on July 31, 2012.  Subsequent to the informal meeting, the protest to HWW’s certificate was withdrawn on August 3, 2012.  Therefore, the application for certificate must be ruled upon by November 5, 2012, pursuant to Section 367.031, F.S.

Staff would note that the customer’s objections mainly concerned the establishment of just and reasonable initial rates and charges.  The withdrawal of the objection was conditioned upon the customer’s understanding that there would be an opportunity to share issues and concerns with staff for consideration in its recommendation on initial rates and charges and that, under the proposed agency action process, there is an opportunity to seek an evidentiary hearing if the customer disagrees with the Commission’s proposed agency action order.  The customer filed specific concerns regarding rates and charges on August 6, 2012.  Staff conducted a noticed, customer meeting in the Harbor Hills community on September 5, 2012, at which time the customer’s questions were addressed.  The customer’s questions and staff’s responses are discussed further in Issue 2.

Land Ownership, Territory, and Maps

Rule 25-30.033(1)(j), F.A.C., requires evidence that the utility owns the land upon which the utility treatment facilities are, or will be, located.  Because a number of affiliated entities were involved in the prior ownership of the Harbor Hills wastewater facilities, a commitment for title insurance issued by First American Title Insurance Company was filed as proof of ownership.  This Commission has relied on title insurance wherever proof of ownership is either by Quit Claim Deed or otherwise clouded.[2]  As such, staff recommends that the Utility has provided adequate proof of ownership.  The application also contains adequate service territory and system maps along with a territory description, as required by Rule 25-30.033(1)(l),(m) and (n), F.A.C.  A description of HWW’s proposed service territory is appended to this recommendation as Attachment A.  As previously discussed, the wastewater territory represents only a small portion of the water territory granted in Certificate No. 522-W.

Technical and Financial Ability

Pursuant to Rule 25-30.033(1)(e), F.A.C., HWW’s application contains statements describing the technical and financial ability of the applicant to provide service to the proposed service area.  According to the application, HWW brings a level of Florida-specific expertise that is not typical for private utility ownership within the State.  The directors of HWW have been in the water and wastewater utility management, operations, and maintenance industry for many years, providing service to more than 450 Florida facilities throughout their careers.  Further, the application indicates that the President and Vice President have 27 and 35 years, respectively, of operation or ownership, including a number of utilities previously regulated by the Commission.  The application indicates that operating, billing, collection, and customer services will be provided by contract through an affiliated entity, U.S. Water Services Corporation, which currently provides such services to approximately 70,000 customers. 

Staff would note that HWW is not the developer of the service territory nor a previously regulated entity.  Instead, it is a private entity established solely for the purpose of owning and operating the Harbor Hills water and wastewater systems.  Also, while, the water system was  regulated by the Commission at the time HWW acquired it, the wastewater system was not.  The application also contains personal financial statements for the President and Vice President of HWW.  The purchase of the wastewater system, $30,000, will be a cash transaction.  Based on the above, it appears that HWW has demonstrated its technical and financial ability to provide service to the proposed territory.

Facilities Description and Compliance

The existing wastewater system is permitted by the Florida Department of Environmental Protection (DEP) for 40,000 gallons per day (gpd), annual average daily flow.  It includes extended aeration treatment consisting of flow equalization, aeration, secondary clarification, chlorination, and aerobic digestion of residuals.  The size of the plant and the wastewater effluent are not adequate to provide reuse.  Instead, the system consists of two rapid infiltration basins for effluent disposal.  During a recent DEP inspection, the wastewater system was cited for a couple of deficiencies regarding fencing and rehabilitating the surfaces of the plant.  Staff conducted its own inspection of the facilities on July 19, 2012, in which it discussed the work being done by HWW to resolve the deficiencies.  In addition, staff has verified with DEP that HWW has been cooperating to bring the system into compliance.

The Buyer is aware that the Utility’s books and records must be maintained in accordance with the National Association of Regulatory Utility Commissioners’ Uniform System of Accounts and that it may not change the Utility’s rates or charges, extend or delete the Utility’s service territory, change the Utility’s name, or transfer the Utility facilities or majority control without Commission approval.  Further, the Buyer has confirmed that it intends to fulfill the commitments, obligations, and representation of the Seller with regard to utility matters, pursuant to Rule 25-30.037(2)(j), F.A.C.

Conclusion

Based on the above information, staff recommends that the application is in the public interest and HWW should be granted Certificate No. 565-S to serve the territory described in Attachment A, effective the date of the Commission’s vote.  The resultant order should serve as HWW’s wastewater certificate and it should be retained by the Utility.

 


Issue 2

 What are the appropriate wastewater service rates and return on equity for HWW?

Recommendation

 Staff’s recommended monthly wastewater rates shown on Schedule No. 2 are reasonable and should be approved.  The Utility should file revised tariff sheets and a proposed customer notice to reflect the Commission-approved rates.  The approved rates should be effective for services rendered on or after the stamped approval date of the revised tariff sheets pursuant to Rule 25-30.475(1), F.A.C.  In addition, the rates should not be implemented until staff has approved the proposed customer notice.  The Utility should provide proof of the date the notice was given within 10 days of the date of the notice.  The Utility should be required to charge the approved rates until a change is authorized by the Commission in a subsequent proceeding.  A return on equity of 10.35 percent, plus or minus 100 basis points, should also be approved.  (Brady, Rieger, Lawson)

Staff Analysis

  Rule 25-30.033(1)(t), (u), (v), and (w), F.A.C., specifies the requirements for establishing rates and charges for original certificates, including the submission of a cost study, growth projections, and data related to the projected plant, capital structure, and operating expenses.  HWW’s proposed wastewater rates are based on projected plant and operations at 80 percent of design capacity, or 200 ERC, which is consistent with Commission policy for setting initial rates and charges. 

Customer Meeting

As noted previously, staff conducted a noticed, customer meeting in the Harbor Hills community on September 5, 2012, to solicit comments on HWW’s proposed wastewater rates.  Staff also explained the rate making process and the assumptions used in establishing initial rates.  Two Harbor Hills residents, as well as representatives from HWW and the developer, attended the meeting.  One of the customers raised questions regarding (1) whether existing customers should receive a credit or reduced bill based on the assumption that their service was paid for in the purchase price of the lots and (2) whether the company could be precluded from filing a rate case prior to reaching 80 percent of its design capacity.  In response to the first question, staff explained that, in the Utility's application, the original investment in the wastewater treatment plant was almost fully depreciated and the cost of the collection system was imputed as contributions in aid of construction (CIAC), pursuant to Rule 25-30.570, F.A.C.  Therefore, the Utility's proposed return on investment and depreciation expense is primarily related to plant improvements made in the past two years and additional plant improvements that are anticipated in the near future.  With respect to the second question, staff explained that the Commission does not have the authority to preclude the Utility from applying for a rate increase once the original certificate has been granted; however, the Commission does look at the prudence of any proposed rate increase.

Projected Rate Base

Consistent with Commission practice in applications for original certificates, projected rate base is established only as a tool to aid the Commission in setting initial rates and is not intended to formally establish rate base.  HWW’s projected wastewater rate base calculations are described below and shown on Schedule No. 1. 

HWW  proposed a projected utility plant in service (UPIS) balance of $2,300,062 shown on Schedule No. 1.  This includes the estimated original cost of the major components of plant and lines, recent additions, and additional plant improvements required by DEP.  In addition, HWW included the projected cost of the collection system, $1,310,784, as CIAC.  The projected CIAC will result in approximately 56 percent contribution level.  Pursuant to Rule 25-30.580, F.A.C., the minimum amount of CIAC should not be less than the percentage of such facilities that is represented by the wastewater collection system and the maximum contribution level should not exceed 75 percent of the projected cost of the plant, net of accumulated depreciation.  In the HWW application, the collection system represents approximately 56 percent of the projected cost of the wastewater system.  Therefore, it appears the project contribution level is consistent with Rule 25-30.580, F.A.C.

HWW’s accumulated depreciation and accumulated amortization of CIAC balances, $1,737,060 and $942,576, respectively, are based on the average service lives guidelines, as set forth in Rule 25-30.140, F.A.C.  Projected working capital is based on one-eighth of the projected operating and maintenance expenses.  Staff recommends that HWW’s projected rate base of $207,377, as shown on Schedule No. 1, is reasonable and should be used in establishing initial wastewater rates and charges.

Projected Cost of Capital

HWW’s projected capital structure consists of 50 percent equity and 50 percent debt.  The utility proposed cost of equity is 10.85 percent.  HWW’s proposed cost of debt is 4.25 percent, based on recent loan experience. 

Staff recommends that the utility’s cost of equity should be based on the most recent leverage graph formula at the time of the Commission vote, 10.35 percent, consistent with prior Commission decisions regarding applications for original certificates.[3]  Based on a cost of equity of 10.35 percent and a cost of debt of 4.25 percent, HWW’s overall cost of capital is 7.30 percent, as shown on the following chart.

Cost of Capital

 

Description

Amount

  Weight

  Cost Rate

Weighted Cost

Equity

$103,688

    50%

  10.35%

5.175%

Debt

$103,689

    50%

    4.25%

2.125%

Overall Cost of Capital

$207,377

  100%

 

7.30%

Range of Reasonableness

 

 

    High

       Low

Return on Common Equity

 

 

  11.35%

         9.35%

 

Staff recommends that the appropriate return on equity for HWW is 10.35 percent, plus or minus 100 basis points, and the Utility’s initial wastewater rates should reflect an overall cost of capital of 7.30 percent.

Projected Net Operating Income

HWW’s projected net operating income of $15,657 was based on a projected overall cost of capital of 7.55 percent.  Using staff’s recommended overall cost of capital of 7.30 percent, staff recommends that a net operating income of $15,138 shown on Schedule No. 1 is reasonable and should be used in establishing initial wastewater rates.

Projected Revenue Requirement

HWW’s projected wastewater revenue requirement of $143,171 is shown on Schedule No. 1.  The revenue requirement includes projected operating and maintenance (O&M) expenses, net depreciation expense, taxes other than income, and a return on investment.  The O&M expenses, which are based on projected operating costs at 80 percent of design capacity, include costs for purchased power, chemicals, contractual services, insurance, and sludge removal.  Staff recommends that HWW’s projected expenses appear reasonable.  However, the revenue requirement should be reduced by $197 to reflect a reduction in the net operating income of $519 associated with the reduced overall return on investment described above.  In addition, it includes an increase in Taxes Other Than Income of $322 to reflect the appropriate regulatory assessment fees associated with the projected revenue requirement.  Therefore, staff recommends a projected revenue requirement of $142,974 should be used in establishing initial wastewater rates, as shown on Schedule No. 1.

Rates and Rate Structure

HWW’s proposed wastewater rates are designed in accordance with Rule 25-30.033(2), F.A.C., which requires that a base facility and usage rate structure, as defined in Rule 25-30.437(6), F.A.C., be utilized for metered service.  Wastewater service is not metered, but usage is based on the customer’s metered water usage.  HWW’s proposed wastewater rates shown on Schedule No. 2 are designed to recover its projected revenue requirement of $143,171.  Based on staff’s recommended projected revenue requirement of $142,974, staff recommends a base facility charge for all residential customers of $29.79, regardless of meter size; and a residential usage charge of $4.85 per 1,000 gallons, with a cap at 6,000 gallons per month.  Staff recommends that the base facility charge for general service customers be based on the actual meter size, as shown on Schedule No. 2; and that the general service usage charge be $5.82 per 1,000 gallons with no cap.  HWW’s proposed and staff’s recommended rates and charges are shown on Schedule No. 2.

Conclusion

Based upon the above, staff recommends that staff’s recommended monthly wastewater rates shown on Schedule No. 2 are reasonable and should be approved.  The Utility should file revised tariff sheets and a proposed customer notice to reflect the Commission-approved rates.  The approved rates should be effective for services rendered on or after the stamped approval date of the revised tariff sheets pursuant to Rule 25-30.475(1), F.A.C.  In addition, the rates should not be implemented until staff has approved the proposed customer notice.  The Utility should provide proof of the date the notice was given within 10 days of the date of the notice.  The Utility should be required to charge the approved rates until a change is authorized by the Commission in a subsequent proceeding.  A return on equity of 10.35 percent, plus or minus 100 basis points, should also be approved.


Issue 3

 What are the appropriate wastewater service availability policy and charges for HWW?

Recommendation

 HWW’s proposed service availability policy and the staff recommended main extension charge of $6,480 are consistent with Rule 25-30.580, F.A.C., and should be approved.  The approved service availability policy and main extension charge should be effective for connections made on or after the stamped approval date on the tariff sheets, pursuant to Rule 25-30.475, F.A.C.  HWW should be required to collect the approved main extension charge until a change is authorized by the Commission in a subsequent proceeding.   (Brady, Rieger)

Staff Analysis

 Pursuant to Rule 25-30.580(1), F.A.C., the maximum amount of CIAC, net of amortization, should not exceed 75 percent of the total original cost, net of depreciation, of the utility’s facilities and plant when the facilities and plant are at their designed capacity.  Rule 25-30.580(2), F.A.C., provides that the minimum amount of CIAC should not be less than the percentage of such facilities that is represented by the wastewater collection system.

            HWW’s proposed wastewater service availability policy provides that future developers should be required to construct and donate the lines necessary to connect to the wastewater system.  In the event that HWW constructs the lines, HWW proposed a main extension charge of $3,803 per ERC.  According to the application, this charge was based on HWW’s estimated value of all costs associated with providing service to its existing wastewater customers ($296,600).  The Utility did not propose a plant capacity charge.

            Instead, staff recommends that the total projected cost of the collection system and pumping equipment needed to serve the wastewater system at build out, $1,295,901, should be used to calculate the appropriate main extension charge.  Therefore, staff recommends a main extension charge of $6,480 per ERC shown on Schedule No. 2. 

            Staff recommends that HWW’s proposed service availability policy and the staff recommended main extension charge of $6,480 are consistent with Rule 25-30.580, F.A.C., and should be approved.  The approved service availability policy and main extension charge should be effective for connections made on or after the stamped approval date on the tariff sheets, pursuant to Rule 25-30.475, F.A.C.  HWW should be required to collect the approved main extension charge until a change is authorized by the Commission in a subsequent proceeding.


Issue 4

 Should HWW’s proposed miscellaneous service charges be approved?

Recommendation

 Yes.  HWW's proposed miscellaneous service charges shown on Schedule No. 2 should be approved and effective for services rendered or connections made on or after the stamped approval date on the tariff sheets, pursuant to Rule 25-30.475, F.A.C.  When both water and wastewater services are provided, a single charge is appropriate unless circumstances beyond the control of the Utility require multiple actions.  HWW should be required to charge its approved miscellaneous service charges until a change is authorized by the Commission in a subsequent proceeding.  (Brady)

Staff Analysis:  Rule 25-30.460, F.A.C., defines the categories of miscellaneous service charges.  The purpose of these charges is to place the burden for requesting or causing these services on the cost causer, rather than the general body of ratepayers.  HWW’s proposed charges for the four categories of wastewater miscellaneous service are based on the approved water miscellaneous service charges for Harbor Hills Utilities, L.P., with the exception of the violation reconnection charge which is actual cost.

 

Miscellaneous Service Charges

Wastewater

Description

Proposed Charges

Initial Connection

$15.00

Normal Reconnection

$15.00

Violation Reconnection

Actual Cost

Premise Visit Charge

$10.00

In addition, HWW has requested authorization to collect an additional miscellaneous service charge when checks are returned for non-sufficient funds.  Instead of a specific charge, HWW proposes that the returned check charge reference the controlling statutes, which are Sections 68.065 and 832.08(5), F.S.  Section 68.065, F.S., allows for the assessment of charges for the collection of worthless checks, drafts, or orders of payment.  As currently set forth in Section 832.08(5), F.S., the following fees may be assessed:

1)         $25, if the face value does not exceed $50, 

2)         $30, if the face value exceeds $50 but does not exceed $300,

3)         $40, if the face value exceeds $300,

4)         or five percent of the face amount of the check, whichever is greater.

Staff believes HWW’s request is appropriate and consistent with recent Commission decisions.[4]

Staff recommends that HWW’s proposed wastewater miscellaneous service charges shown on Schedule No. 2 are reasonable and should be approved and effective for services rendered or connections made on or after the stamped approval date on the tariff sheets, pursuant to Rule 25-30.475, F.A.C.  When both water and wastewater services are provided, a single charge is appropriate unless circumstances beyond the control of the Utility require multiple actions.  HWW should be required to charge its approved miscellaneous service charges until a change is authorized by the Commission in a subsequent proceeding.


Issue 5

 Should this docket be closed?

Recommendation

 Yes.  The certification portion of this recommendation will become final agency action upon the Commission's vote.  If no timely protest to the proposed agency action portions of this recommendation with respect to initial rates and charges is filed with the Commission by a substantially affected person, a Consummating Order should be issued and the docket should be closed administratively.  (Lawson)

Staff Analysis

 The certification portion of this recommendation will become a final agency action upon the Commission's vote.  If no timely protest to the proposed agency action portions of this recommendation with respect to initial rates and charges is filed with the Commission by a substantially affected person, a Consummating Order should be issued and the docket should be administratively closed.



Harbor Waterworks, Inc.

Description of Wastewater Territory

in

Lake County

 

 

Township 18 South, Range 24 East

Section 13

 

Township 18 South, Range 25 East

Sections 7 and 18

 

The following described lands located in portions of Section 13, Township 18 South, Range 24 East, and Sections 7 & 18, Township 18 South, Range 25 East, Lake County, Florida:

 

Begin at the Southeast corner of Section 12, Township 18 South, Range 24 East, for the Point of Beginning; thence run North 00°07'21" West, along the East boundary of said Section 12 a distance of 66.62 feet to the centerline of Lake Griffin Road and a point on a curve having a radial bearing of North 27°13'16" West, said curve being concave Northwesterly having a radius of 615.63 feet; thence run Easterly along said centerline an arc distance of 228.02 feet, said arc having a delta of 21º13'18", a tangent distance of 115.33 feet, a chord bearing of North 52°10'04" East and a chord distance of 226.72 feet to a point of tangency; thence run North 41º33'27" East along said centerline a distance of 403.94 feet to a point of curvature, said curve being concave Northwesterly having a radius of 1,730.29 feet; thence run Northeasterly along said centerline an arc distance of 240.35 feet, said arc having a delta of 07°57'32", a tangent distance of 120.37 feet, a chord bearing of North 37°34'41" East and a chord distance of 240.16 feet to a point of tangency; thence run North 33°35'55" East along said centerline a distance of 88.27 feet to a point of curvature, said curve being concave Southeasterly having a radius of 234.54 feet; thence run Easterly along said centerline an arc distance of 307.05 feet, said arc having a delta of 75°00'30", a tangent distance of 180.00 feet, a chord bearing of North 71°06'10" East and a chord distance of 285.59 feet to a point of tangency; thence run South 71°23'35" East along said centerline a distance of 606.85 feet to a point of curvature, said curve being concave Northeasterly having a radius of 919.44 feet; thence run Easterly along said centerline an arc distance of 249.03 feet, said arc having a delta of 15°31'06", a tangent distance of 125.28 feet, a chord bearing of South 79°09'08" East and a chord distance of 248.27 feet to a point of tangency; thence run South 54°48'39" East a distance of 221.30 feet; thence run South 35°11'21" West a distance of 2,009.33 feet; thence run North 51°43'05" West a distance of 422.00 feet; thence run South 89°55'26" West a  distance of 400.37 feet to a point on the East boundary of Section 13; thence run North 00°04'34" West along the East boundary of Section 13 a distance of 165.41 feet; thence run North 89°58'35" West a distance of 526.35 feet; thence run North 66°26'23" West a distance of 357.90 feet; thence run North 00°01'25" East a distance of 634.92 feet to a point on the South boundary of Section 12; thence run North 89°40'50" East a distance of 853.12 feet along the South boundary of Section 12 to the Point of Beginning.


FLORIDA PUBLIC SERVICE COMMISSION

 

authorizes

 

Harbor Waterworks, Inc.

pursuant to

Certificate Number 565-S

 

to provide wastewater service in Lake County in accordance with the provisions of Chapter 367, Florida Statutes, and the Rules, Regulations, and Orders of this Commission in the territory described by the Orders of this Commission.  This authorization shall remain in force and effect until superseded, suspended, cancelled or revoked by Order of this Commission.

 

Order Number                         Date Issued      Docket Number           Filing Type

 

*                                              *                      120158-SU                  Original Certificate

 

 

*Order Number and date to be provided at time of issuance.



Harbor Waterworks, Inc.

Wastewater System

 

 

 

Projected Wastewater Rate Base

 

 

 

Utility Proposed

 

Adjustments

Staff Recommended

Utility Plant in Service

 

$  2,300,062

 

$  2,300,062

Accumulated Depreciation

 

(1,737,060)

 

(1,737,060)

Contributions in Aid of Construction

 

(1,310,784)

 

(1,310,784)

Accum Amort of CIAC

 

942,576

 

942,576

Working Capital Allowance

 

        12,583

 

        12,583

Wastewater Rate Base

 

$     207,377

 

$     207,377

 

 

 

Projected Wastewater Revenue Requirement

 

 

 

Utility Proposed

 

Adjustments

Staff Recommended

Operating Revenues

 

$     143,171

(197)

$     142,974

Operating and Maintenance

 

96,366

 

96,366

Net Depreciation Expense

 

23,036

 

23,036

Taxes Other Than Income

 

         8,112

322

         8,434

Operating Income

 

$       15,657

(519)

$       15,138

Wastewater Rate Base

 

$     207,377

 

$     207,377

Rate of Return

 

7.55%

 

7.30%


Harbor Waterworks, Inc.

Wastewater System

 

Monthly Residential and General Service Wastewater Rates

 

 

Utility Proposed

 

Staff Recommended

Base Facility Charge

 

 

 

Residential (all meter sizes)

$         29.83

 

$         29.79

General Service (based on meter size)

 

 

 

     5/8" x 3/4”

$         29.83

 

$         29.79

                3/4”

44.75

 

44.69

                   1”

74.58

 

74.48

                1.5”

149.15

 

148.95

                   2”

238.64

 

238.32

                   3”

447.45

 

476.64

                   4”

745.75

 

744.75

                   6”

1,491.50

 

1,489.50

Residential charge per 1,000 gallons

$         4.86*

 

$        4.85*

General Service charge per 1,000 gallons

$           5.83

 

$         5.82

* 6,000 gallon cap per month

 

 

 

 

Comparison of Monthly Residential Wastewater Bills

 

 

Utility Proposed

 

Staff Recommended

  3,000 gallons

$ 44.41

 

$44.34

  5,000 gallons

$ 54.13

 

$54.04

10,000 gallons

$ 58.99

 

$58.89

 

Wastewater Service Availability Charges

 

 

Utility Proposed

 

Staff Recommended

Main Extension Charge

 

 

 

     Residential – per ERC 160 gpd

$3,803

 

$ 6,480

     All others – per gallon

$23.77

 

$ 40.50

 

Wastewater Miscellaneous Service Charges**

Initial Connection Charge

 

$    15.00

Normal Reconnection Charge

 

$    15.00

Violation Reconnection Charge

 

Actual Cost

Premises Visit in Lieu of Disconnection Charge

 

$    10.00

Returned Check Charge

 

Per Statute

   (Sections 68.065 and 832.08(5), F.S.)

 

 

**  When both water and wastewater services are provided, a single charge is appropriate unless

      circumstances beyond the control of the Utility require multiple actions.



[1] In re:  Application for approval of transfer of Harbor Hills Utility, L.P. water system and Certificate No. 522-W in Lake County to Harbor Waterworks, Inc.

[2] See Order No. PSC-03-0787-FOF-WS, issued July 2, 2003, in Docket No. 020091-WS, In re: Application for transfer of majority organizational control of Service Management Systems, Inc., holder of Certificates Nos. 517-W and 450-S in Brevard County, from Petrus Group, L.P. to IRD Osprey, LLC d/b/a Aquarina Utilities.

[3] Order No. PSC-12-0339-PAA-WS, issued June 28, 2012, in Docket No. 120006-WS, In re: Water and wastewater industry annual reestablishment of authorized rate of return on common equity for water and wastewater utilities pursuant to Section 367.081(4)(f), F.S.

[4] Order No. PSC-10-0364-TRF-WS, issued June 7, 2010, in Docket No. 100170-WS, In re: Application for authority to collect non-sufficient funds charges, pursuant to Sections 68.065 and 832.08(5), F.S., by Pluris Wedgefield, Inc. and Order No. PSC-10-0474-TRF-WS, issued July 28, 2010, in Docket No. 100313-WS, In re: Application for authority to collect non-sufficient funds charges, pursuant to Sections 68.065 and 832.08(5), F.S., by Utilities, Inc.