State of Florida

pscSEAL

 

Public Service Commission

Capital Circle Office Center ● 2540 Shumard Oak Boulevard
Tallahassee, Florida 32399-0850

-M-E-M-O-R-A-N-D-U-M-

 

DATE:

May 26, 2016

TO:

Office of Commission Clerk (Stauffer)

FROM:

Division of Engineering (Lee)

Office of the General Counsel (Murphy)

RE:

Docket No. 160073-EQ – Petition for approval of amended standard offer contract (Schedule COG-2), by Duke Energy Florida, LLC.

AGENDA:

06/09/16Regular Agenda – Proposed Agency Action – Interested Persons May Participate

COMMISSIONERS ASSIGNED:

All Commissioners

PREHEARING OFFICER:

Administrative

CRITICAL DATES:

None

SPECIAL INSTRUCTIONS:

Staff recommends the Commission simultaneously consider Docket Nos. 160069-EQ, 160072-EQ, and 160073-EQ.

 

 Case Background

Section 366.91(3), Florida Statutes (F.S.), requires that each investor-owned utility (IOU) continuously offers to purchase capacity and energy from renewable generating facilities and small qualifying facilities. Florida Public Service Commission (Commission) Rules 25-17.200 through 25-17.310, Florida Administrative Code (F.A.C.), implement the statute and require each IOU to file with the Commission by April 1 of each year, a standard offer contract based on the next avoidable fossil fueled generating unit of each technology type identified in the utility’s current Ten-Year Site Plan. On April 1, 2016, Duke Energy Florida, LLC. (DEF) filed a petition for approval of its standard offer contract based on its 2016 Ten-Year Site Plan. The Commission has jurisdiction over this standard offer contract pursuant to Sections 366.04 through 366.06 and 366.91, F.S.


Discussion of Issues

Issue 1: 

 Should the Commission approve the revised standard offer contract and schedule COG-2 filed by Duke Energy Florida, LLC.?

Recommendation: 

 Yes. The provisions of DEF’s revised standard offer contract and schedule COG-2 conform to all requirements of Rules 25-17.200 through 25-17.310, F.A.C. DEF’s revised standard offer contract provides flexibility in the arrangements for payments so that a developer of renewable generation may select the payment stream best suited to its financial needs. (Lee)

Staff Analysis: 

 Rule 25-17.250, F.A.C., requires that DEF, an IOU, continuously makes available a standard offer contract for the purchase of firm capacity and energy from renewable generating facilities (RF) and small qualifying facilities (QF) with design capacities of 100 kilowatts (kW) or less. Pursuant to Rule 25-17.250(1) and (3), F.A.C., the standard offer contract must provide a term of at least 10 years, and the payment terms must be based on the utility’s next avoidable fossil-fueled generating unit identified in its most recent Ten-Year Site Plan or, if no avoided unit is identified, its next avoidable planned purchase.

DEF has identified an 849 megawatt (MW) natural gas-fueled combustion turbine (CT) facility as its next planned generating unit in its 2016 Ten-Year Site Plan. The projected in-service date of the unit is June 1, 2024.

The RF/QF operator may elect to make no commitment as to the quantity or timing of its deliveries to DEF, and to have a committed capacity of zero (0) MW. Under such a scenario, the energy is delivered on an as-available basis and the operator receives only an energy payment. Alternatively, the RF/QF operator may elect to commit to certain minimum performance requirements based on the identified avoided unit, such as being operational and delivering an agreed upon amount of capacity by the in-service date of the avoided unit, and thereby becomes eligible for capacity payments in addition to payments received for energy. The standard offer contract may also serve as a starting point for negotiation of contract terms by providing payment information to an RF/QF operator, in a situation where one or both parties desire particular contract terms other than those established in the standard offer.

In order to promote renewable generation, the Commission requires each IOU to offer multiple options for capacity payments, including the options to receive early or levelized payments. If the RF/QF operator elects to receive capacity payments under the normal or levelized contract options, it will receive as-available energy payments only until the in-service date of the avoided unit (in this case June 1, 2024), and thereafter begin receiving capacity payments in addition to the energy payments. If either the early or levelized option is selected, then the operator will begin receiving capacity payments earlier than the in-service date of the avoided unit. However, payments made under the early capacity payment options tend to be lower in the later years of the contract term because the net present value (NPV) of the total payments must remain equal for all contract payment options.

Table 1 below, estimates the annual payments for each payment option available under the revised standard offer contract to an operator with a 50 MW facility operating at a capacity factor of 95 percent, which is the minimum capacity factor required under the contract to qualify for full capacity payments. Normal and levelized capacity payments begin in 2024, reflecting the projected in-service date of the avoided unit (June 1, 2024).

 

 

Table 1 – Estimated Annual Payments to a 50 MW Renewable Facility

(95% Capacity Factor)

Year

Energy Payment

Capacity Payment (By Type)

Normal

Levelized

Early

Early Levelized

$(000)

$(000)

$(000)

$(000)

$(000)

2017

15,088

-

-

-

-

2018

15,560

-

-

-

-

2019

15,690

-

-

-

-

2020

16,384

-

-

-

-

2021

18,086

-

-

-

-

2022

20,049

-

-

2,185

2,510

2023

21,004

-

-

2,239

2,513

2024

21,877

1,688

1,917

2,295

2,517

2025

22,502

2,967

3,291

2,352

2,521

2026

23,457

3,041

3,296

2,411

2,525

2027

23,553

3,117

3,301

2,472

2,529

2028

24,388

3,195

3,306

2,533

2,533

2029

25,442

3,275

3,311

2,597

2,537

2030

25,801

3,356

3,317

2,662

2,542

2031

26,813

3,440

3,323

2,728

2,546

2032

27,531

3,526

3,328

2,796

2,551

2033

28,505

3,614

3,334

2,866

2,555

2034

29,647

3,705

3,340

2,938

2,560

2035

30,825

3,797

3,347

3,011

2,565

2036

31,837

3,892

3,353

3,087

2,570

Total

464,040

42,614

41,764

39,172

38,073

NPV (2017$)

235,340

17,211

17,211

17,211

17,211

 

 

DEF’s revised tariff sheets of the standard offer contract, in type-and-strike format, are included as Attachment A to this recommendation. All of the changes made to DEF’s tariff sheets are consistent with the updated avoided unit. Revisions include updates to the avoided unit, dates, and payment information which reflect the current economic and financial assumptions for the avoided unit costs. Other changes are primarily intended for clarification purposes.

Conclusion

The provisions of DEF’s revised standard offer contract and schedule COG-2 conform to all requirements of Rules 25-17.200 through 25-17.310, F.A.C. DEF’s revised standard offer contract provides flexibility in the arrangements for payments so that a developer of renewable generation my select the payment stream best suited to its financial needs. Staff recommends that DEF’s revised standard offer contract and related rate schedule be approved as filed.



Issue 2:  Should this docket be closed?

Recommendation: Yes. This docket should be closed upon issuance of a consummating order, unless a person whose substantial interests are affected by the Commission’s decision files a protest within 21 days of the issuance of the Commission’s Proposed Agency Action Order. Potential signatories should be aware that, if a timely protest is filed, DEF’s standard offer contract may subsequently be revised. (Murphy)

Staff Analysis: This docket should be closed upon the issuance of a consummating order, unless a person whose substantial interests are affected by the Commission’s decision files a protest within 21 days of the issuance of the Commission’s Proposed Agency Action Order. Potential signatories should be aware that, if a timely protest is filed, DEF’s standard offer contract may subsequently be revised.