-M-E-M-O-R-A-N-D-U-M-

 

DATE:

June 29, 2017

TO:

Office of Commission Clerk (Stauffer)

FROM:

Division of Engineering (Matthews, Thompson)

Office of the General Counsel (Murphy)

RE:

Docket No. 170075-EQ – Petition for approval of revisions to standard offer contract and rate schedule COG-2, by Tampa Electric Company.

AGENDA:

07/13/17 – Regular Agenda – Proposed Agency Action – Interested Persons May Participate

COMMISSIONERS ASSIGNED:

All Commissioners

PREHEARING OFFICER:

Administrative

CRITICAL DATES:

None

SPECIAL INSTRUCTIONS:

Staff recommends the Commission simultaneously consider Docket Nos. 170070-EQ, 170072-EQ, 170076-EQ, & 170077-EQ

 

 Case Background

Section 366.91(3), Florida Statutes (F.S.), requires that each investor-owned utility (IOU) continuously offers to purchase capacity and energy from renewable energy generators and small qualifying facilities. Florida Public Service Commission (Commission) Rules 25-17.200 through 25-17.310, Florida Administrative Code (F.A.C.), implement the statute and require each IOU to file with the Commission by April 1 of each year, a standard offer contract based on the next avoidable fossil fueled generating unit of each technology type identified in the utility’s current Ten-Year Site Plan. On March 31, 2017, Tampa Electric Company (TECO) filed a petition for approval of its revised standard offer contract and rate schedule COG-2 based on its 2017 Ten-Year Site Plan. The Commission has jurisdiction over this standard offer contract pursuant to Sections 366.04 through 366.06 and 366.91, F.S.


Discussion of Issues

Issue 1: 

 Should the Commission approve the revised standard offer contract and schedule COG-2 filed by Tampa Electric Company?

Recommendation: 

 Yes. The provisions of TECO’s revised standard offer contract and schedule COG-2 conform to all requirements of Rules 25-17.200 through 25-17.310, F.A.C. TECO’s revised standard offer contract provides flexibility in the arrangements for payments so that a developer of renewable generation may select the payment stream best suited to its financial needs. Staff recommends that TECO’s revised tariff sheets for the standard offer contract and revised schedule COG-2 be approved as filed. (Thompson)

Staff Analysis: 

 Rule 25-17.250, F.A.C., requires that TECO, an IOU, continuously make available a standard offer contract for the purchase of firm capacity and energy from renewable generating facilities (RF) and small qualifying facilities (QF) with design capacities of 100 kilowatt (kW) or less. Pursuant to Rule 25-17.250(1) and (3), F.A.C., the standard offer contract must provide a term of at least 10 years, and the payment terms must be based on the Utility’s next avoidable fossil-fueled generating unit as identified in its most recent Ten-Year Site Plan, or if no avoided unit is identified, its next avoidable planned purchase. TECO has identified a 220 megawatt (MW) natural gas-fired combustion turbine as its next avoidable fossil-fueled generating unit in its 2017 Ten-Year Site Plan. The projected in-service date of the unit is May 1, 2021.

 

The RF/QF operator may elect to make no commitment as to the quantity or timing of its deliveries to TECO, and to have a committed capacity of zero (0) MW. Under such a scenario, the energy is delivered on an as-available basis and the operator receives only an energy payment. Alternatively, the RF/QF operator may elect to commit to certain minimum performance requirements based on the identified avoided unit, such as being operational and delivering the agreed upon amount of capacity by the in-service date of the avoided unit, and thereby becomes eligible for capacity payments in addition to payments received for energy. The standard offer contract may also serve as a starting point for negotiation of contract terms by providing payment information to an RF/QF operator, in a situation where one or both parties desire particular contract terms other than those established in the standard offer.

In order to promote renewable generation, the Commission requires an IOU to offer multiple options for capacity payments, including the options to receive early or levelized payments. If the RF/QF operator elects to receive capacity payments under the normal or levelized contract options, it will receive as-available energy payments only until the in-service date of the avoided unit (in this case, May 1, 2021), and thereafter will receive capacity payments in addition to the energy payments. If either the early or levelized option is selected, then the operator will begin to receive capacity payments earlier than the in-service date of the avoided unit. However, payments made under the early capacity payment option tend to be lower in the later years of the contract term because the net present value (NPV) of the total payments must remain equal for all contract payment options.  

 

Table 1 below, estimates the annual payments for each payment option available under the revised standard offer contract to an operator with a 50 MW facility, operating at an 80 percent capacity factor, which is the minimum capacity factor required to qualify for full capacity payments. Normal and levelized capacity payments begin 2021, reflecting the projected in-service date of the avoided unit (May 1, 2021).

 

 

Table 1- Estimated Annual Payments to a 50 MW Renewable Facility

(80% Capacity Factor)

Year

Energy Payment

Capacity Payment (By Type)

Normal

Levelized

Early

Early Levelized

$(000)

$(000)

$(000)

$(000)

$(000)

2018

9,107

-

-

 2,793

 3,278

2019

10,999

-

-

 2,862

 3,289

2020

12,097

-

-

 2,933

 3,301

2021

12,324

 2,626

 3,011

 3,006

 3,313

2022

12,912

 4,005

 4,527

 3,081

 3,326

2023

12,772

 4,104

 4,543

 3,157

 3,338

2024

13,570

 4,206

 4,560

 3,236

 3,351

2025

14,486

 4,310

 4,578

 3,316

 3,364

2026

14,948

 4,417

 4,595

 3,398

 3,378

2027

15,736

 4,527

 4,613

 3,483

 3,392

2028

16,419

 4,640

 4,632

 3,569

 3,406

2029

16,987

 4,755

 4,651

 3,658

 3,421

2030

18,284

 4,873

 4,670

 3,749

 3,436

2031

19,128

 4,994

 4,690

 3,842

 3,451

2032

19,451

 5,118

 4,710

 3,937

 3,466

2033

21,217

 5,245

 4,731

 4,035

 3,482

2034

22,769

 5,375

 4,753

 4,135

 3,499

2035

21,767

 5,509

 4,774

 4,238

 3,516

2036

21,651

 5,645

 4,797

 4,343

 3,533

2037

22,082

 5,785

 4,820

 4,451

 3,550

Total

328,706

 80,133

 77,656

 71,222

 68,091

NPV (2018$)

169,445

 38,306

 38,306

 38,306

 38,306

Source: TECO’s Response to Staff’s First Data Request[1]

 

TECO’s revised tariff sheets for the standard offer contract, in type-and-strike format, are included in Attachment A. All of the changes made to the tariff sheets are consistent with the updated avoided unit. Revisions include updates to the avoided unit, dates, and payment information which reflect the current economic and financial assumptions for the avoided unit.

Conclusion

The provisions of TECO’s revised schedule COG-2 for the standard offer contract conform to all of the requirements of Rules 25-17.200 through 25-17.310, F.A.C. The revised standard offer contract provides flexibility in the arrangements for payments so that a developer of renewable generation may select the payment stream best suited to its financial needs. Staff recommends that TECO’s revised tariff sheets for the standard offer contract and revised schedule COG-2 be approved as filed.


Issue 2: 

 Should this docket be closed?

Recommendation: 

 Yes. This docket should be closed upon issuance of a consummating order, unless a person whose substantial interests are affected by the Commission’s decision files a protest within 21 days of the issuance of the Commission’s Proposed Agency Action Order. Potential signatories should be aware that, if a timely protest is filed, TECO’s standard offer contract may subsequently be revised. (Murphy)

Staff Analysis: 

 This docket should be closed upon the issuance of a consummating order, unless a person whose substantial interests are affected by the Commission’s decision files a protest within 21 days of the issuance of the Commission’s Proposed Agency Action Order. Potential signatories should be aware that, if a timely protest is filed, TECO’s standard offer contract may subsequently be revised.



 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 



[1]Document No. 05111-17, dated May 31, 2017, in Docket No. 170075-EQ.