State of Florida
|
Public Service Commission Capital Circle Office Center ● 2540 Shumard
Oak Boulevard -M-E-M-O-R-A-N-D-U-M- |
||
|
DATE: |
|||
|
TO: |
Office of Commission Clerk (Teitzman) |
||
|
FROM: |
Division of Economics (Nguyen, Hampson) Office of the General Counsel (Brownless) |
||
|
RE: |
|||
|
AGENDA: |
12/01/26 – Regular Agenda – Tariff Filing – Interested Persons May Participate |
||
|
COMMISSIONERS ASSIGNED: |
|||
|
PREHEARING OFFICER: |
|||
|
SPECIAL INSTRUCTIONS: |
|||
On September 3, 2026, Tampa Electric Company (TECO or utility) filed a petition seeking approval to implement its 2027 subsequent year adjustment (SYA). The Commission previously approved the 2027 SYA in its final order addressing TECO’s request for base rate increase, Order No. PSC-2025-0038-FOF-EI (Rate Case Order).[1] Pages 150-169 of the Rate Case Order discuss the 2027 SYA, including the specific projects and their associated incremental operating and maintenance expense, depreciation expense, and investment tax credit amortization. Based on Commission-approved adjustments to each of the projects, the total 2027 SYA revenue requirement is $9,089,346.[2]
The Rate Case Order further required TECO to file its proposed 2027 SYA rates for approval in September 2026, with rates effective the first billing cycle of January 2027. In addition, the Rate Case Order required TECO to verify the in-service dates of all projects and use the then-current billing determinants.
By Order No. PSC-2026-0358-PCO-EI, the Commission suspended the proposed tariffs for further review by staff. During evaluation of the petition, staff issued two data requests to the utility, for which responses were received on October 15 and November 5, 2026.[3] This is staff’s recommendation to approve the proposed 2027 SYA and associated tariffs. The Commission has jurisdiction over this matter pursuant to Sections 366.04, 366.041, 366.05, and 366.06, Florida Statutes.
Issue 1:
Should
the Commission approve TECO's proposed rates and associated tariffs to
implement its 2027 subsequent year adjustment?
Recommendation:
Yes. The Commission should approve TECO’s proposed rates and associated tariffs to implement its 2027 SYA, because the project timelines, rates, and associated tariffs are consistent with the Commission’s prior decision in the Rate Case Order. The rates have been calculated to recover a total 2027 SYA revenue requirement of $9,089,346 as previously approved by the Commission and as presented in Exhibit 1 of TECO’s petition. Consistent with the Rate Case Order, the associated tariffs, included as Attachment A to this recommendation, should become effective with the first billing cycle of January 2027. (Nguyen)
Staff Analysis:
With respect to the project timelines, TECO stated that the South Tampa Resilience Project went into service on December 15, 2025, the Polk Unit 4 Fuel Diversity upgrade is expected to be in service in November 2026, and the Polk Unit 5 Fuel Diversity upgrade was placed into service on August 8, 2026. TECO submitted sworn affidavits in support thereof. In response to staff’s discovery, TECO provided additional detail regarding the in-service dates identified in the Rate Case Order, most recent anticipated in-service dates, and an explanation for any adjustments to the projects. All relevant projects are on track to meet the timeframes contained in the Rate Case Order.
TECO’s petition included the proposed tariff sheets, the allocation of the revenue increase to the various rate classes, and calculations showing the revenue from the sale of electricity by rate schedule under current and proposed rates. Consistent with the Rate Case Order, the total amount to be collected through the 2027 SYA is $9,089,346. Exhibit 1 of TECO’s petition presents a calculation of this amount. Also, consistent with the Rate Case Order, TECO states that the utility used the most recent billing determinants, which were also used for TECO’s cost recovery clause projection filings, to calculate the 2027 SYA base rates.[4] Furthermore, staff compared the billing determinants used to calculate the 2027 SYA to the billing determinants from TECO’s cost recovery clause projection and confirmed that they are equivalent.
The base rate portion of a monthly residential electric bill for 1,000 kilowatt-hours would increase from $102.98 to $103.54, which is an increase of $0.56. In response to staff’s second data request, TECO stated they would provide notice of the proposed rate increase to customers with its December bills.
Conclusion
The Commission should approve TECO’s proposed rates and associated tariffs to implement the 2027 SYA because the project timelines, rates, and associated tariffs are consistent the Commission’s prior decision in the Rate Case Order. The rates have been calculated to recover a total 2027 SYA revenue requirement of $9,089,346 as previously approved by the Commission and as presented in Exhibit 1 of TECO’s petition. Consistent with the Rate Case Order, the associated tariffs, included as Attachment A to this recommendation, should become effective with the first billing cycle of January 2027.
Issue 2:
Should
this docket be closed?
Recommendation:
If Issue 1 is approved and a protest is filed within 21 days of the issuance of the Order by a person whose substantial interests are affected, the tariff should remain in effect, with any incremental revenues held subject to refund, pending resolution of the protest. If no timely protest is filed, this docket should be closed upon the issuance of a Consummating Order. (Brownless)
Staff Analysis:
If Issue 1 is approved and a protest is filed within 21 days of the issuance of the Order by a person whose substantial interests are affected, the tariff should remain in effect, with any incremental revenues held subject to refund, pending resolution of the protest. If no timely protest is filed, this docket should be closed upon the issuance of a Consummating Order.








































[1] Order No. PSC-2025-0038-FOF-EI, issued February 3, 2025, in Docket Nos. 20240026-EI, 20230139-EI, and 20230090-EI, In re: Petition for rate increase by Tampa Electric Company.
[2] Ibid., page 167.
[3] Document No. 07353-2026, filed October 15, 2026, Document No. 07735-2026, filed November 5, 2026.
[4] Page 3, paragraph 9 of the petition.